Electronic procurement planning and procurement performance in Wakiso District Local Government, Uganda. A cross-sectional study.

Authors

  • Stella Nakanwagi School of Graduate Studies and Research, Team University
  • Dr. Moses Muhwezi School of Graduate Studies and Research, Team University
  • Edmand Bakashaba School of Graduate Studies and Research, Team University

DOI:

https://doi.org/10.70572/3k17wb47

Keywords:

Electronic Procurement Planning, Electronic Government Procurement, Procurement Performance, Local Government, Wakiso District

Abstract

Background:

Procurement planning is the first stage of the procurement cycle, so weaknesses in it are carried into later stages. This study examined the contribution of electronic procurement planning to procurement performance in Wakiso District Local Government.

 Methodology:

A cross-sectional correlational design with a convergent mixed-methods approach was used. Fieldwork was carried out on 25–27 October 2026. Data came from 80 of 89 sampled staff (response rate 89.9%) through a five-point Likert questionnaire, from interviews with three key informants, and from a review of procurement records for FY 2021/22 to FY 2025/26. Analysis used descriptive statistics, Pearson and Spearman correlations, regression, and thematic analysis.

 Results:

Most respondents were male (63.7%), aged 25–54 years (85.0%), held a bachelor's, postgraduate diploma, or master's degree (78.8%), and had used e-GP (92.5%). Electronic planning was rated moderate (M = 3.27) and procurement performance high (M = 3.54). Electronic planning was positively but weakly related to performance (r = .358, p = .001), explaining 12.8% of its variance. It was related most strongly to transparency and accountability (r = .389) and timeliness (r = .350), but not to value for money. Records showed that average requisition-to-award time rose from 95 to 110 days. Heads of user departments rated planning lowest (M = 3.05), compared with PDU staff (M = 3.71).

 Conclusion:

Electronic procurement planning is positively but weakly related to procurement performance. Its contribution is limited when requisitions are late, plans are not updated, and inputs are inaccurate.

 Recommendation:

The Chief Administrative Officer and the PDU should set an annual deadline for submitting requirements to the e-GP planning module, update plans whenever priorities change, and provide role-based refresher training. Budget coding should also be aligned with the IFMS.

Author Biographies

  • Stella Nakanwagi, School of Graduate Studies and Research, Team University

    is a researcher at the School of Graduate Studies and Research, Team University

  • Dr. Moses Muhwezi, School of Graduate Studies and Research, Team University

    is a research supervisor at the School of Graduate Studies and Research, Makerere University

References

1. Amin, M. E. (2005). Social science research: Conception, methodology and analysis. Kampala, Uganda: Makerere University Press.

2. Basheka, B. C. (2008). Procurement planning and accountability of local government procurement systems in developing countries: Evidence from Uganda. Journal of Public Procurement, 8(3), 379-406. https://doi.org/10.1108/JOPP-08-03-2008-B005

3. Braun, V., & Clarke, V. (2006). Using thematic analysis in psychology. Qualitative Research in Psychology, 3(2), 77-101. https://doi.org/10.1191/1478088706qp063oa

4. Creswell, J. W., & Creswell, J. D. (2018). Research design: Qualitative, quantitative, and mixed methods approaches (5th ed.). SAGE Publications.

5. Cronbach, L. J. (1951). Coefficient alpha and the internal structure of tests. Psychometrika, 16(3), 297-334. https://doi.org/10.1007/BF02310555

6. Croom, S., & Brandon-Jones, A. (2007). Impact of e-procurement: Experiences from implementation in the UK public sector. Journal of Purchasing and Supply Management, 13(4), 294-303. https://doi.org/10.1016/j.pursup.2007.09.015

7. Konneh, A. (2024). The impact of procurement planning on service delivery in the Inspectorate of Government of Kampala, Uganda. Research Invention Journal of Law, Communication and Languages, 3(1), 51-61.

8. Krejcie, R. V., & Morgan, D. W. (1970). Determining sample size for research activities. Educational and Psychological Measurement, 30(3), 607-610. https://doi.org/10.1177/001316447003000308

9. Polit, D. F., & Beck, C. T. (2006). The content validity index: Are you sure you know what's being reported? Critique and recommendations. Research in Nursing & Health, 29(5), 489-497. https://doi.org/10.1002/nur.20147

10. Public Procurement and Disposal of Public Assets Authority. (2026). Guideline No. 2 of 2026 on Electronic Government Procurement (eGP). Government of Uganda.

11. Tornatzky, L. G., & Fleischer, M. (1990). The processes of technological innovation. Lexington Books.

Downloads

Published

2026-11-24

Issue

Section

Section of Humanities

How to Cite

Nakanwagi, S., Muhwezi, M., & Edmand Bakashaba. (2026). Electronic procurement planning and procurement performance in Wakiso District Local Government, Uganda. A cross-sectional study. AfroGlobal Perspectives, 3(11), 15. https://doi.org/10.70572/3k17wb47